Representational Image (Photo: Indian Railways)
New Delhi, Nov 24: The Railways ministry has initiated the land acquisition process for the proposed 69.05-km Kokrajhar-Gelephu railway line project in Assam, issuing a notification declaring its intention to acquire 58.217 hectares of land in Kokrajhar and Chirang districts.
The notification, issued by the ministry through the Northeast Frontier Railway’s Construction Organisation, marks an important step towards taking forward the railway connectivity project linking Kokrajhar in Assam with Gelephu in Bhutan.
The ministry had last month appointed the Bodoland Territorial Council (BTC) secretary as the competent authority for the execution, maintenance, management and operation of the special railway project.
According to the land acquisition notification, out of a total recorded area of 216.742 hectares, 58.217 hectares have been identified for acquisition for the railway project.
The areas include privately owned land as well as government land spread across several villages under Sidli West mouza. The notification provides details of landowners, survey or dag numbers, total land holdings and the specific areas proposed to be acquired.
As part of the statutory process, the notification gives individuals interested in the identified land 30 days from the date of publication in the official gazette to submit objections against the proposed acquisition and use of their land.
The objections have to be submitted in writing, specifying the grounds, to the Competent Authority for Land Acquisition (CALA), BTC. The competent authority will provide the objectors an opportunity to be heard, either personally or through a legal practitioner.
The acquisition exercise will affect multiple landowners in villages including Amguri, Batabari and Shyamthaibari, besides other identified land parcels.
The largest identified land acquisition components include 11.7987 hectares in Amguri, 10.2233 hectares in Batabari and 5.2035 hectares in Shyamthaibari. The notification also lists land parcels in other areas, taking the total proposed acquisition to 58.217 hectares.
The project assumes significance as the railway line is expected to strengthen connectivity between Assam’s Bodoland Territorial Region and Bhutan’s Gelephu region. Gelephu is being developed by Bhutan as a major economic and urban development destination under its Gelephu Mindfulness City initiative